ADU electrical requirements in Sacramento

An ADU adds a dwelling’s worth of load. The right design is a load calculation — not an automatic 200-amp service or a second meter.

Solar-ready main panel with backfeed breaker position

Available 24 hours

Licensed C-10 · CSLB #1115460

Emergency electrical
10 sections
  1. Start with the ADU loads
  2. How it is supplied
  3. 200A service
  4. Load calculation
  5. Which loads matter
  6. Subpanel size
  7. Breaker space
  8. SMUD and permits
  9. The ADU electrical planning
  10. Before a quote

An ADU adds another dwelling’s worth of electrical load to a property. That does not automatically mean the main house needs a 200-amp service, a second utility service, or a completely separate meter. The right design depends on whether the ADU is attached or detached; how it will be heated and cooled; whether cooking and water heating are electric; whether laundry is included; whether EV charging is planned; how much capacity the existing service has; and how the owner wants the ADU metered and operated. The useful question is what electrical loads will the ADU actually have, and what is the cleanest way to supply them? That decision should happen before walls are framed around an undersized electrical plan.

The planning order is:

define ADU → equipment → inventory main house → load calculation → supply strategy → physical route → permit/utility → branch circuits
ItemCurrent planning baseline
Design basisCombined property load calculation, not an assumed panel size
200A serviceCommon and often useful, not automatic
100A serviceNot automatically disqualified
SubpanelDoes not create additional utility capacity
Attached vs detachedDifferent feeder, route, grounding, and construction cost
Supply optionsExisting service plus ADU subpanel; service upgrade; load management; separate utility arrangement
KitchenCircuit-intensive; settle appliances before the electrical plan
EV chargingCan become the tipping point
PermitADU building permit, not a collection of minor electrical permits
SMUDInvolve early when service or metering changes
Utility vs buildingLocal inspection approval before SMUD energization

Start with the ADU loads, not the panel size

A small ADU can still be electrically demanding. An all-electric unit with an induction range, electric oven, heat-pump HVAC, heat-pump water heater, electric dryer, dishwasher, microwave, general receptacles, and lighting can be a much larger electrical load than a similarly sized unit using gas for cooking, water heating, and space heating. Square footage matters less than the actual equipment: a 500-square-foot ADU with several large electric loads can require more electrical capacity than a larger unit with modest equipment.

Attached and detached ADUs are different electrical projects. An attached ADU may be relatively close to the home’s existing electrical equipment. A detached ADU may require a feeder across the property, underground conduit, a dedicated subpanel, grounding-electrode provisions, trenching, and utility coordination if separately served. That changes both the electrical design and the construction cost. The electrical route should therefore be part of early ADU planning, not something decided after the floor plan is finished.

How is the ADU supplied?

The ADU can share the existing service through a dedicated subpanel, or it can be designed around separate metering or a separate service. Decide that before the feeder route, electrical room, and utility work are locked in.

Feed the ADU from the existing main service. For many ADUs, the simplest arrangement is existing utility service → main house electrical equipment → feeder → ADU subpanel. The ADU then has its own distribution panel while remaining part of the property’s existing electrical service. This can work well when the existing service has enough calculated capacity, the feeder route is practical, separate utility metering is not required, and the owner is comfortable with the ADU sharing the main service. A dedicated ADU subpanel can still provide clear circuit separation even though both dwellings share one utility service.

A subpanel is not a second service. An ADU subpanel receives power from upstream electrical equipment. It does not create additional utility capacity by itself. If the property has a 100A service and a 100A ADU subpanel is installed, the property has not become a 200A service. The total demand still has to fit within the capacity of the upstream service. The subpanel rating describes the panel or feeder arrangement. The service rating describes what the utility connection and service equipment can supply.

Separate utility metering or service is a different project. Possible reasons include owner preference, tenant utility separation, physical layout, utility requirements, service-capacity constraints, and future property-use planning. This is not simply an electrician adding another meter socket wherever convenient. SMUD controls the connection to its distribution system and designates acceptable service and meter locations. SMUD’s residential service standards state that normally only one service point is granted to one building or parcel, while multiple service points may be allowed when they meet electrical-code, utility, and local-jurisdiction requirements. So a proposed second service needs to be coordinated with SMUD early.

Do not decide on a second meter after construction starts. Meter and service location can affect site layout, trenching, panel placement, clearances, conduit, utility construction, and cost. SMUD assigns an engineering designer to applicable service projects and determines the service point and meter requirements. If a separately served ADU is being considered, that conversation should happen before the electrical room, exterior walls, hardscape, or landscaping make the utility route difficult.

Does an ADU require a 200A main service?

No. A 200A service is common and often useful, but the ADU itself does not automatically trigger that number. The correct test is a load calculation. Possible outcomes include the existing 100A service remaining adequate, the existing 125A or 150A service remaining adequate, a 200A upgrade being justified, load management helping, a separate service being the stronger design, or a service larger than 200A requiring consideration. The answer depends on the combined electrical demand of the house and ADU.

100A may work — but future loads matter. Suppose an existing house has a 100A service with a gas furnace, water heater, range, and dryer. A modest ADU with efficient electric equipment might still be possible depending on the calculation. But if the owner also plans to electrify the main house later with a heat pump, induction cooking, electric water heating, and EV charging, designing only for today’s load may create a second service project shortly afterward. A good plan considers known future loads before choosing the final service arrangement.

200A is not unlimited. A 200A service can support a lot of residential load. It is still finite. A main house plus ADU can consume substantial capacity when both are all-electric and the property also includes two EV chargers, a spa, pool equipment, a workshop, solar battery equipment, and multiple HVAC systems. If the calculated demand approaches the service limit, the design may need load management, different equipment choices, a larger service, or a separate service configuration. Do not assume 200A automatically resolves every ADU project.

Services above 200A require additional utility planning. SMUD’s residential service requirements include separate provisions for residential service above 200 amps. That does not mean a typical ADU needs more than 200A. It means that if the calculation or project configuration points above 200A, the design should not be treated as a routine 200A upgrade. Utility requirements become more important.

What goes into the load calculation?

The calculation should account for both existing and proposed loads. On the main house, that can include lighting and receptacle load, kitchen circuits, laundry, HVAC, water heating, cooking, dryer, spa or pool, EV charging, existing detached structures, and other fixed loads. On the ADU, that can include lighting, general receptacles, kitchen small-appliance circuits, cooking, refrigerator, dishwasher, disposal, microwave, HVAC, water heating, laundry, bathroom loads, EV charging, and other fixed equipment.

The calculation applies permitted demand factors rather than assuming every connected appliance runs at full output simultaneously. That is why simply adding breaker sizes is not a valid service calculation.

Which ADU loads drive the calculation?

Cooking, water heating, HVAC, laundry, and EV charging drive the load calculation more than square footage. Select the actual equipment — or realistic worst-case values — before the service and feeder are sized.

Plan the kitchen first. The kitchen is one of the most circuit-intensive parts of an ADU. Depending on the design, electrical planning may include countertop small-appliance circuits, refrigerator, dishwasher, disposal, microwave, range or cooktop, wall oven, range hood, under-cabinet lighting, and island or peninsula receptacles. A compact kitchen can therefore require a surprising number of branch circuits. Appliance selections should be settled before the electrical plan is finalized. Changing from gas cooking to induction late in the project can materially change the load calculation.

Cooking equipment can change the service decision. An ADU with a gas range has a very different electrical profile from one with an induction cooktop, electric range, or electric wall oven. If the project is intended to be all-electric, the cooking load should be included from the beginning. Do not plan the service around a placeholder appliance and then select a much larger electric range after permit drawings are complete.

Water heating matters. Water heating can be one of the largest loads in a small dwelling. Common options include a gas water heater, a conventional electric resistance tank, a heat-pump water heater, and an electric tankless water heater. These are not electrically equivalent. An electric tankless water heater can require very substantial electrical capacity compared with a heat-pump water heater. If service capacity is tight, water-heater selection can materially change whether an upgrade is needed.

HVAC needs a real equipment selection. “Mini-split” is not a complete electrical specification. The electrical plan should be based on the actual equipment or realistic design values: voltage, minimum circuit ampacity, maximum overcurrent protection, number of indoor/outdoor units, backup or resistance heating, and disconnect requirements. A small heat pump can be relatively modest. Electric resistance backup heat can change the load substantially.

Laundry can add another large circuit. If the ADU includes laundry, decide whether the dryer is gas, conventional electric, heat-pump electric, or a combination washer/dryer. A conventional electric dryer typically creates a much larger branch-circuit load than a heat-pump dryer. In a capacity-constrained project, appliance choice can be a design tool rather than an afterthought.

EV charging can become the tipping point. The ADU may not need a service upgrade by itself. The ADU plus EV charging might. This is especially relevant when the main house already has an EV charger and the ADU will have separate parking. Possible strategies include lower-amperage Level 2 charging, energy management, shared charging capacity, reserving conduit for future charging without installing the full load now, and a service upgrade. The goal should be to design for the actual vehicle use rather than automatically installing the largest charger possible.

Future EV capacity should still be considered. Even if no charger is installed during construction, new construction is the easiest time to plan for it. Future preparation can include a conduit route, panel space, feeder capacity, load-management provisions, and parking-location coordination. That can be much cheaper than cutting finished surfaces and trenching later. Future-ready does not necessarily mean energizing a 60A EV circuit on day one.

Use real appliance specifications before final electrical plans. One of the easiest ways to create redesign work is to use generic placeholders. Before the electrical design is finalized, collect specifications for the range or cooktop, oven, microwave, dishwasher, water heater, HVAC, dryer, EV charger if planned, and other large fixed appliances. The electrician can then design around actual loads and manufacturer requirements. If equipment has not been selected, use realistic worst-case design assumptions rather than unrealistically small placeholder loads.

Next step

Plan the ADU electrical first

Send the ADU floor plan if you have it, photos of the existing panel with the door open, and the loads you expect — range, HVAC, dryer, EV. That is enough to start the calculation.

How large should the ADU subpanel be?

There is no universal answer. Common panel ratings may include 60A, 100A, 125A, or other sizes appropriate to the design. The panel should be selected around calculated ADU load, feeder size, number of branch circuits, future expansion, equipment availability, and physical space. A larger-rated panel can provide more breaker spaces without necessarily meaning the feeder or service has the same amperage. Again, panel rating and available electrical capacity are not interchangeable.

Do not undersize the panel just because the ADU is small. A small enclosure with too few breaker spaces can become frustrating quickly. An ADU may need individual circuits for kitchen small appliances, dishwasher, disposal, microwave, range, refrigerator, laundry, bathroom, HVAC, water heater, lighting, general receptacles, and exterior loads. Add possible future circuits and a “tiny house” can consume a substantial number of breaker positions. Adequate breaker space is inexpensive during initial construction compared with replacing an undersized panel later.

Detached ADU feeders require more planning. A detached ADU feeder can involve trenching, conduit, feeder conductors, grounding, disconnecting means, panel placement, voltage drop, and other underground utilities. The distance matters. A feeder to a detached structure at the back of a deep lot is different from feeding an attached conversion a few feet from the main panel. Longer runs can influence conductor sizing and project cost.

Grounding and bonding are not the same thing. A detached ADU may involve both an equipment grounding conductor run with the feeder and grounding-electrode requirements at the structure itself — related but not interchangeable, and a grounding electrode at the ADU does not replace the equipment grounding path back with the feeder. In the ADU subpanel, neutral conductors stay isolated from the equipment-grounding system while equipment grounds bond to the enclosure; bonding neutral and ground together again downstream puts normal return current onto grounding paths that should not carry it. That is why “just add a subpanel” is not merely installing another box and moving breakers — where the system bonding point sits is part of the electrical design, not an improvisation in the ADU panel.

Does the main panel have enough breaker space?

Capacity and physical space are separate questions. A service can have enough calculated capacity but the existing panel may not have enough usable breaker positions for the ADU feeder. Possible solutions include reconfiguration where permitted, panel replacement, additional distribution equipment, and an appropriate feeder arrangement. Do not confuse “no empty breaker slot” with “not enough service capacity.” One is a distribution-space problem. The other is a load problem.

An old panel can change the project. An ADU is a substantial new electrical addition. If the main house still has Zinsco, Federal Pacific Stab-Lok, damaged panel equipment, badly overcrowded equipment, or obsolete service hardware, the ADU project is a good time to decide whether that equipment should remain the upstream source. The answer should come from condition, suitability, and project scope rather than brand name alone. Sometimes panel replacement is justified without increasing service amperage. Sometimes the ADU also makes a service upgrade sensible. Those are separate decisions.

How do SMUD and building permits work for an ADU?

SMUD’s current design-and-construction process specifically tells customers planning an ADU or secondary dwelling to review utility planning requirements to avoid redesign costs and delays. For projects that need new service or an upgrade, SMUD may need to review the project, assign an engineering designer, determine the service point, identify meter location, identify required utility work, issue project requirements, and coordinate energization. The local building department still handles the electrical permit and inspection. These are parallel processes.

Utility approval and building approval are separate. For service work, the local agency typically handles the building permit, plan review, and electrical inspection; SMUD handles the service application, utility design, service requirements, meter/service work, and energization. SMUD’s current meter-and-service process requires local agency inspection approval before SMUD completes final meter/service energization. An ADU project that changes the utility service therefore needs both sides coordinated.

The permit is an ADU building permit, not just an electrical permit. A new ADU is a dwelling-unit construction project. Its electrical work is integrated into the overall building permit. In the City of Sacramento, ADUs require building-permit review, and the City provides ADU resources and permit-ready plans for qualifying projects. The electrical scope is reviewed as part of that permitted construction. Do not treat the ADU like a collection of unrelated minor electrical permits.

Sacramento now encourages early ADU zoning review. The City has streamlined its ADU process and provides an optional zoning review before the building-permit application. That can help confirm objective zoning standards before substantial design work is completed. For electrical planning, that matters because changes to ADU location, footprint, detached vs attached configuration, parking, and the utility route can all affect the electrical design. A final electrical feeder route should not be based on an ADU location that may later move.

The ADU electrical planning sequence

A clean ADU electrical process looks like this:

  1. Define the ADU — attached or detached, size, and intended use.
  2. Select major equipment — cooking, HVAC, water heating, laundry, and EV charging.
  3. Inventory the main house — service rating, panel condition, existing large loads, and future planned loads.
  4. Perform the load calculation — main house plus ADU, with future loads where relevant.
  5. Choose the supply strategy — existing service and ADU subpanel, service upgrade, load management, or a separate utility configuration.
  6. Plan the physical route — panel locations, feeder path, trenching, meter location, and utility requirements.
  7. Coordinate permit and utility review — local building department, and SMUD where required.
  8. Finalize equipment and branch circuits — before rough wiring.

That sequence avoids many of the expensive late changes: choosing the panel before calculating the load, assuming 200A is mandatory or always enough, forgetting the main house’s future electrification, selecting appliances after permit drawings, treating a subpanel as added service capacity, waiting too long to contact SMUD, forgetting EV charging, undersizing breaker space, and treating neutral and ground as interchangeable.

Questions to answer before accepting an ADU electrical quote

A useful proposal should answer:

  1. What is the existing service rating?
  2. What is the calculated existing load?
  3. What is the calculated ADU load?
  4. Does the service size need to change?
  5. Is the ADU fed from a subpanel or separately served?
  6. What feeder size is proposed?
  7. Where will the ADU panel be located?
  8. How many breaker spaces will it have?
  9. Which appliances receive dedicated circuits?
  10. Is EV charging included or future-prepared?
  11. Does SMUD need to modify service equipment?
  12. Are permit and inspection included?
  13. Is trenching included?
  14. Are drywall or finish repairs included?
  15. What known future loads were included in the design?

If those questions are unanswered, the electrical scope is probably not mature enough.

What to gather before the electrical walkthrough. Bring the ADU floor plan, site plan, appliance schedule, HVAC specifications, water-heater specifications, range/cooktop information, laundry equipment, EV plans, photos of the main electrical equipment, main breaker rating, solar/battery information if present, and future electrification plans for the main house. For a detached ADU, also identify the likely route between the main electrical equipment, the ADU, the parking area, and the utility service point. That makes the first electrical conversation much more useful.

ADU electrical work in Sacramento: what to do next

An ADU electrical system should be designed around the combined property load, not an assumed panel size. The main choices are usually to feed the ADU from the existing service through a dedicated subpanel; upgrade the main service if the calculation requires it; use load management where appropriate; or coordinate a separate utility arrangement when that is the better project design.

A 100A service is not automatically disqualified. A 200A service is not automatically required. And installing a large subpanel does not create more service capacity.

For Sacramento-area ADUs, the best time to settle these questions is before final plans and construction: establish the major appliance loads, calculate the house and ADU together, decide how the ADU will be supplied, and involve SMUD early if the project changes service or metering.

Litel Electric can review the existing electrical service, calculate the proposed loads, plan the ADU feeder and panel, identify required branch circuits, and coordinate the electrical scope with the permit and utility requirements.

See Electrical panel upgrade.

Call (279) 972-9272.

Sources

Get estimate

Tell us what is happening, or what you are planning. We read the details, tell you what else we need to know, and explain the next step before anything is scheduled.

  1. 01

    You send the problem or the plan, with the address if you have it.

  2. 02

    We reply with what it involves and what has to be seen in person.

  3. 03

    Nothing is scheduled, and nothing is priced, until the equipment has been looked at.

License
CSLB #1115460 · C-10 electrical